    BORAL | SYDNEY AGGREGRATES

  • BORAL SYDNEY AGGREGATES PROJECT – PEPPERTREE, MEDWAY & MALDON SITES

    The scope of works for Peppertree included:

    • Design, supply & construct 1.2km of new track for Balloon Loop
    • Design, supply & construct 1.2km of new track to South Marulan Quarry & install 2 new turnouts
    • Removal of 60 joints, weld and adjust track
    • Installing lubricator and friction modifier locations
    • Install “Armco” barrier ballast retaining walls at culvert
    • Resurfacing


    The scope of works for Medway included:

    • Re-railing of 650m of track
    • Reconditioning of 170m of track
    • Design, supply and construction of 1.2km of track and associated drainage and earthworks
    • Supply and construction of new 2 turnouts
    • Removing and re-instate staff hut
    • Installation of 4 x 2.4m span box culvert on both tracks to replace the existing timber bridge
    • Removal of 30 x joints
    • Weld and adjust track
    • Install lubricators


    The scope of works for Maldon included:

    • Extend siding by 173m
    • Re-railing through the proposed dump station
    • Extend embankment by 95m to accommodate the new trackwork
    • Construct new buffer stop
    • Weld and adjust track
    • Resurfacing