ASC | CRANE RAIL PROJECT
PORT BOTANY TERMINAL 3 - SUPPLY AND INSTALLATION OF ASC RAIL SYSTEM
The scope of works for the ASC project included the design and construction of a rail beam along a concrete beam for the Automatic Stacking Cranes to run. The programmed works were split as follows:
- ASC 4 & 5 commenced in April 2014 with a 30 week construction period. For ASC 4 one rail was supplied as follows:
Supply to 3 beams of 330m each;
Install to 4 Beams of 330m each;
- ASC6 commenced in March 2015 with a 20 week construction period. Supply and installation included two 330m beams
Works were completed on time and budget was met- ASC 4 & 5 commenced in April 2014 with a 30 week construction period. For ASC 4 one rail was supplied as follows:
© 2018